(Updated Nov. 30, 2020)
Date authorized: May 05, 2016
Project Authorization: $11,107,000
Delivery Method: Construction Manager as constructor (CMc)
Design Firm: The Clark Enersen Partners
Construction Manager: Titan Built, LLC
Completion Date: Q4 2021 (substantial completion)
Future Pending Action(s): Approve Guaranteed Maximum Price (GMP) Amendment for Construction.
Update: The project remains on schedule with Construction Documents completing in December. Bids will be received in January, with action for the GMP Amendment anticipated on February 4, 2021. Construction is expected to begin in February and substantial completion is anticipated Q4 2021.