(Updated Nov. 30, 2020)
Date authorized: Project approved through Capital Improvement Plan
Project Authorization: $1,373,950
Delivery Method: Design, Bid, Build
Design Firm: Confluence
Contractor: Combes Construction LLC.
Completion Date: Substantial completion September 8, 2020
Future Pending Action(s): No action required from BOCC
Update: Combes Construction LLC. began construction in February 2020. The development will take place where the Shawnee Mission Park Visitor Center was located before being razed. The project includes a shade structure, landscaping, walkways, parking and realignment of the park road to improve traffic flow near the park entrance. The contractor has completed the construction with the exception of two minor issues noted by the city codes inspector. The contractor is now correcting those issues.